How we inspected 300,000 litres of water without draining a drop
At NDT Group, we love a challenge. Our technicians are always ready to think outside the box and develop inventive solutions to complex inspection problems.
So, when a long-standing client in the aerospace industry approached us with an unusual request, we were more than happy to rise to the occasion.
This client requested an inspection of a water tank with a difference. Usually, we would drain the water from the tank, but the client wanted us to inspect the tank without the need to drain 300,000 litres of water.
Our team got to work and came up with a solution. The result was well-executed and the client was pleased with the outcome.
Their problem: an inspection with a twist
Our client needed to carry out an inspection of a large water storage tank, but there was one major complication – they didn’t want to drain the 300,000 litres of water inside.
Traditionally, tank inspections require the water to be removed so that technicians can manually assess the internal condition. However, this process is costly, time-consuming, and environmentally wasteful.
The client wanted a solution that would keep the water in place while still delivering accurate inspection results.To add to the complexity, they required a Fit for Purpose report in line with EEMUA 159 guidance. Typically, this would also be carried out on an empty tank, so we needed to find a creative way to meet the requirements without traditional access.
Our solution
Rather than relying on conventional methods, our team devised a cutting-edge approach using underwater drone technology. We deployed a high-resolution 4K camera-equipped drone to ‘swim’ inside the tank, capturing clear visuals of the tank’s internal condition without disturbing a single drop of water.
In addition to the drone survey, we performed Ultrasonic Testing (UT) using a submersible UT probe and pole system. This allowed us to take precise thickness measurements of the tank walls, ensuring a comprehensive assessment of their integrity.
The result: cost saving and environmental benefits
Our innovative approach delivered exactly what the client needed – a detailed Fit for Purpose report without the logistical headache of draining and refilling the tank. The client was not only impressed with the quality of the inspection but also delighted with the significant cost and environmental savings.
With multiple tanks on site, the potential long-term benefits are substantial. By eliminating the need to drain vast amounts of water for each inspection, the client stands to save significant resources while ensuring the continued integrity of their assets.
Another successful project, another happy client – and proof that when it comes to inspections, innovation makes all the difference.
Our innovative approach delivered exactly what the client needed - a detailed Fit for Purpose report without the logistical headache of draining and refilling the tank.